The June 6 Building Committee meeting has been moved back one week and rescheduled for June 13. The June 13 meeting will begin one hour later than usual, at 6 pm.
Lyme Town Campus Center
Tuesday, June 4, 2013
June Building Committee Meeting Date Changed
The June 6 Building Committee meeting has been moved back one week and rescheduled for June 13. The June 13 meeting will begin one hour later than usual, at 6 pm.
Thursday, May 23, 2013
Monday's Building Committee Meeting
After the town meeting on Monday night, Building Committee
chair, Dan Hagan presented a status update on the town hall and library project
and answered questions from the audience.
For those who missed the meeting, the following is a summary of the
points that were covered.
Copies of the latest floor plans and site plan can be viewed and downloaded from the links in the right sidebar. The titles include "May 2013".
Copies of the latest floor plans and site plan can be viewed and downloaded from the links in the right sidebar. The titles include "May 2013".
·
Dan began by introducing Wayne Czarnecki, one of
the project managers from Enterprise Builders, and Jake Smith, also with
Enterprise Builders, who will be the on-scene construction supervisor for the
project. Jake will be on site every day
during construction solving problems and making sure that everything runs
smoothly.
Enterprise Builders has been hired as the project’s construction manager. The company is located in Newington, CT, but one of the principals, Keith Czarnecki, lives in Old Lyme and has children in the school system. He knows the area and is excited about the project.
As construction manager, Enterprise Builders will give the town a guaranteed maximum price to build the new library and renovate the town hall.
Enterprise Builders has been hired as the project’s construction manager. The company is located in Newington, CT, but one of the principals, Keith Czarnecki, lives in Old Lyme and has children in the school system. He knows the area and is excited about the project.
As construction manager, Enterprise Builders will give the town a guaranteed maximum price to build the new library and renovate the town hall.
·
The design is complete. The Building Committee will meet on June 6 to
approve the final construction documents which will allow the project to go out
to bid in mid-to-late June. Enterprise
Builders will coordinate the bidding process.
Bids will be opened publicly at town hall, and Enterprise will use the
accepted bids to calculate a guaranteed maximum price for the project. Throughout the period of construction, the
town will hold the contingency funds.
·
The anticipated date to start construction is
around July 21. From start to finish,
building is expected to take 13 months.
·
There will be two construction zones during the
first part of the project. The first is
the area around the new library which will be enclosed in a construction fence. A
truck entrance onto Route 156 will be created.
Enterprise Builders will make sure that the entrance will accommodate the
town’s fire and emergency vehicles.
Drivers will have to be careful when passing the truck entrance, but the library construction area shouldn’t impact the use of the town hall and library. The library will stay in its current building until the new one is finished. After the library moves, the old building will be demolished.
Drivers will have to be careful when passing the truck entrance, but the library construction area shouldn’t impact the use of the town hall and library. The library will stay in its current building until the new one is finished. After the library moves, the old building will be demolished.
·
The second area, which encompasses the town hall,
is more complicated because it is a renovation and an addition. In the first phase, the old church building
where the town clerk’s and first selectman’s offices are currently located will
remain untouched. This will be the
temporary town hall. Town employees will
double up, and a temporary building will be placed in front of the town hall. It will serve as the town’s meeting room
during construction.
The rest of the building will be cordoned off. Renovation will begin on the area which presently houses the building department, planning and zoning, and the meeting room. At the same time, work will begin on the addition which will include offices and the new vault. The vault will be 400 sq. ft., which is the size required for a town the size of Lyme. The current vault is 100 sq. ft.
The phasing plan will make things more inconvenient than some others considered, and the community will have to put up with an unsightly temporary building in front of town hall, but it will shorten the project which in turn, saves money.
The rest of the building will be cordoned off. Renovation will begin on the area which presently houses the building department, planning and zoning, and the meeting room. At the same time, work will begin on the addition which will include offices and the new vault. The vault will be 400 sq. ft., which is the size required for a town the size of Lyme. The current vault is 100 sq. ft.
The phasing plan will make things more inconvenient than some others considered, and the community will have to put up with an unsightly temporary building in front of town hall, but it will shorten the project which in turn, saves money.
·
Once the addition and renovated section are
finished, the town hall staff will move into their news offices. The items in
the vault will probably be moved over a long weekend so that the town records
will remain available to the public. Some
items in the attic will also be moved to the vault. At this point, the work will begin on the
church building. It will be turned into
the new town meeting room. The
renovations include removing the walls and ceilings of the current offices and
restoring the approximately 26 foot tin ceilings.
·
Work is expected to go smoothly. The library is a new building and is
essentially a residential build. There
are just a few pieces of steel. Both the
town hall and old library have been carefully examined, and lead paint and asbestos
noted. There should be few surprises.
·
Once the project if finished, the stone wall
along Route 156 will be restored and there will be just one entrance to serve
both the town hall and library.
·
The Lyme School’s baseball field with be moved
back toward the tennis courts this summer or early fall. The current diamond is partially on Town of
Lyme property, and the land is needed for the town hall addition. The building committee is working closely
with the school district, and the school administration has approved the plan.
·
The parking in front of the library and on the
side of town hall will remain available during construction. The construction plans include expanded
parking for both buildings – approximately 24 spaces for the library and 22 for
the town hall. The parking area will be
laid out with white lines.
·
At this time, there is not a lot of money in the
budget for landscaping. The area will be
graded and seeded. Plans also involve
moving the war memorial and saving some of the current plants and landscape
materials. The Building Committee is
working with both garden clubs in town.
It is possible that the Lyme Garden Club will have the funds to hire a
landscape architect to create a plan and to purchase some plants.
The construction phasing is detailed and well thought out,
and it will be executed by experienced people; however, it is flexible enough
that as issues arise, it will be adjusted.
Residents who see a problem are asked to go to Ralph Eno or Dan Hagan
rather than to Jake. As Dan noted, “Jake
doesn’t need 2,500 bosses.”
Sunday, May 19, 2013
Minutes of the May 2, 2013 Meeting
![]() |
| Spotted along Tantumorantum |
The minutes of the May 2, 2013 Building Committee meeting are available on the Building Committee page of this blog or here.
Friday, May 17, 2013
Public Meeting on Monday, May 20
The Town Campus Building Committee is holding a public meeting on Monday, May 20, 2013. The public is encouraged to attend. Committee chair Dan Hagan will summarize progress to date and how construction is likely to affect day-to-day life in the Town of Lyme.
The meeting will start immediately after the annual town meeting. The town meeting will begin at 7:30 at the Lyme Consolidated School.
Thursday, May 9, 2013
More Town Hall Photos
Thanks to a grant, the town has been able to hire a consultant to prepare the application for historic status. Rachel has been researching the history of the building, and the Lyme Local History Archives has yielded more photos.
![]() | |
| Pleasant Valley Baptist Church circa 1900 Courtesy of the Lyme Local History Archives |
![]() |
| Pleasant Valley Baptist Church and Red House Courtesy of the Lyme Local History Archives |
![]() | |
| North Lyme Baptist Church Courtesy of the Lyme Local History Archives |
Labels:
Archives,
Town Hall - History
Saturday, May 4, 2013
April Minutes
![]() |
| Cherry Blossoms - Off Joshuatown Road |
The minutes of the April meetings of the Town Campus Building Committee are now available on the Building Committee page of this blog.
Tuesday, April 30, 2013
May Building Committee Meeting
The next meeting of the Town Campus Center Building Committee will be on Thursday, May 2, 2013. The meeting will be at the Lyme Town Hall and begin at
5 pm. Visitors are welcome.
Subscribe to:
Posts (Atom)







_1.jpg)